  "edition": "1.0",
  "program_id": "mq25",
  "name": "MQ-25 Stingray",
  "pno": "462",
  "reviewed_at": "2026-09-12",
  "evidence_cutoff": "2026-09-12T15:30:00Z",
  "time_zone": "America/New_York",
  "scope": "MQ-25 Air System and explicitly relevant carrier integration; not complete UMCS or whole-program accounting",
  "sources": [
    {
      "id": "s01",
      "publisher": "Department of the Navy / WHS",
      "title": "MQ-25 FY2027 President’s Budget MSAR",
      "url": "https://www.esd.whs.mil/Portals/54/Documents/FOID/Reading%20Room/Selected_Acquisition_Reports/PB_2027_MSARs/MQ-25_MSAR_FY2027_PBv2.pdf",
      "document_date": "2026-04-21",
      "date_precision": "day",
      "locator": "PDF and printed pages 1 (cover), 5 (mission), 7–9 (history), 10–11 (schedule), 12 (performance), 13 and 15 (acquisition estimate / unit costs), 16 (funding crosswalk), 18–19 (O&S and assumptions), 22–23 (EMD contract), 24 (LRIP), 25 (deliveries / funding / fielding).",
      "reviewed_at": "2026-09-12",
      "original_receipt": {
        "retrieved_at": "2026-09-12T13:55:58.046461+00:00",
        "sha256": "46e0dee54578081bee55326dba82d3c5f39a96bf1e773ae8534d2f3e077dc7f6",
        "http_last_modified": "Wed, 29 Jul 2026 18:52:22 GMT",
        "receipt_filename": "mq25-msar-pb2027.pdf"
      },
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:17.116851+00:00",
        "status": 403
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash.",
      "date_limit": "Cover effective date precedes April 22 modification and April 25 / May 18 actual events; HTTP Last-Modified is not proven publication date."
    },
    {
      "id": "s02",
      "publisher": "NAVAIR",
      "title": "Navy awards Boeing $805.3 million contract to design, build MQ-25A Stingray",
      "url": "https://www.navair.navy.mil/news/navy-awards-boeing-8053-million-contract-design-build-mq-25a-stingray/wed-11142018-2130",
      "document_date": "2018-08-30",
      "date_precision": "day",
      "locator": "Opening two paragraphs: August 30 award, $805.3m ceiling, four aircraft and IOC by 2024. Page publication label takes precedence over the November date embedded in the migrated URL.",
      "reviewed_at": "2026-09-12",
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:19.806783+00:00",
        "status": 403
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash.",
      "browser_review": {
        "date": "2026-09-12",
        "format": "Browser-retriever text, not original HTML bytes."
      }
    },
    {
      "id": "s03",
      "publisher": "Director, Operational Test & Evaluation",
      "title": "FY2025 Annual Report — MQ-25 chapter",
      "url": "https://www.dote.osd.mil/Portals/97/pub/reports/FY2025/Other/2025Annual-Report.pdf",
      "document_date": "2026-03",
      "date_precision": "month",
      "locator": "PDF pp. 188–190 / printed pp. 177–179. Page 177 opening receipt statement; p. 178 Program and Test Adequacy; pp. 178–179 Performance and Recommendation. Retrospective FY2025 assessment, with November 2025 TEMP update.",
      "reviewed_at": "2026-09-12",
      "original_receipt": {
        "retrieved_at": "2026-09-12T13:56:19.890777+00:00",
        "sha256": "b684f515b0471b2616ec8961f64c4987b7d9b7965fbf6e7d051d1f832483c550",
        "http_last_modified": "Fri, 20 Mar 2026 14:16:12 GMT",
        "receipt_filename": "dote-fy2025.pdf"
      },
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:19.218493+00:00",
        "status": 403
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash."
    },
    {
      "id": "s04",
      "publisher": "U.S. Navy / NAVAIR",
      "title": "MQ-25 conducts first air-to-air refueling with F-35C",
      "url": "https://www.navy.mil/Press-Office/News-Stories/display-news/Article/2773685/mq-25-conducts-first-air-to-air-refueling-with-f-35c/",
      "document_date": "2021-09-14",
      "date_precision": "day",
      "locator": "Opening paragraph identifies Boeing-owned T1; paragraph beginning ‘The integrated Navy and Boeing’ dates the F-35C event September 13; paragraph beginning ‘Earlier this summer’ identifies F/A-18 and E-2D demonstrations.",
      "reviewed_at": "2026-09-12",
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:20.122873+00:00",
        "status": 403,
        "url_note": "The one-shot direct request had a mq25/mq-25 slug typo as well as a 403 response; the canonical URL shown here was separately opened successfully through the browser retriever."
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash.",
      "browser_review": {
        "date": "2026-09-12",
        "format": "Browser-retriever text, not original HTML bytes."
      }
    },
    {
      "id": "s05",
      "publisher": "NAVAIR",
      "title": "Navy completes initial carrier demo for MQ-25 program",
      "url": "https://www.navair.navy.mil/news/Navy-completes-initial-carrier-demo-MQ-25-program/Wed-12152021-1336",
      "document_date": "2021-12-20",
      "date_precision": "day",
      "locator": "Paragraphs beginning ‘The government team’ and ‘Once underway’: T1 carrier integration and day/night deck handling. This is not a carrier flight announcement.",
      "reviewed_at": "2026-09-12",
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:20.210258+00:00",
        "status": 403
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash.",
      "browser_review": {
        "date": "2026-09-12",
        "format": "Browser-retriever text, not original HTML bytes."
      }
    },
    {
      "id": "s06",
      "publisher": "NAVAIR",
      "title": "MQ-25A Stingray achieves successful first flight",
      "url": "https://www.navair.navy.mil/news/MQ-25A-Stingray-achieves-successful-first-flight-advancing-future-naval-aviation/Sun-04262026",
      "document_date": "2026-04-27",
      "date_precision": "day",
      "locator": "First two body paragraphs: flight on April 25, approximately two hours, UMCS MD-5 control, basic flight controls, engine performance and handling.",
      "reviewed_at": "2026-09-12",
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:20.037083+00:00",
        "status": 403
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash.",
      "browser_review": {
        "date": "2026-09-12",
        "format": "Browser-retriever text, not original HTML bytes."
      }
    },
    {
      "id": "s07",
      "publisher": "U.S. Navy",
      "title": "Navy’s MQ-25A Stingray secures Milestone C approval",
      "url": "https://www.navy.mil/Press-Office/News-Stories/display-news/Article/4495731/navys-mq-25a-stingray-secures-milestone-c-approval/",
      "document_date": "2026-05-19",
      "date_precision": "day",
      "locator": "Opening paragraph announces Milestone C / transition to LRIP. Exact decision date May 18 comes from MSAR pp. 8, 10, 24, not the May 19 news date.",
      "reviewed_at": "2026-09-12",
      "original_receipt": {
        "retrieved_at": "2026-09-12T13:56:21.410839+00:00",
        "sha256": "b7e97b87d76cf86fbf6848f30e2d0dc35776b3d73654b50b4dd1e5d6e18298ae",
        "http_last_modified": null,
        "receipt_filename": "mq25-milestone-c-2026.html"
      },
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:19.455766+00:00",
        "status": 403
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash.",
      "browser_review": {
        "date": "2026-09-12",
        "format": "Browser-retriever text, not original HTML bytes."
      }
    },
    {
      "id": "s08",
      "publisher": "U.S. Government Accountability Office",
      "title": "Weapon Systems Annual Assessment, GAO-26-108457",
      "url": "https://www.gao.gov/assets/gao-26-108457.pdf",
      "document_date": "2026-07",
      "date_precision": "month",
      "locator": "PDF pp. 163–164 / printed pp. 151–152. Page 152 Program Performance, Software and Cybersecurity, Other Program Issues, and Program Office Comments; earlier review position followed by April/May event updates.",
      "reviewed_at": "2026-09-12",
      "original_receipt": {
        "retrieved_at": "2026-09-12T13:56:12.343318+00:00",
        "sha256": "f9afddd66fcaefe7c6f91dcf644a836a6b971fb792217c601cbc3d37adaac610",
        "http_last_modified": "Thu, 02 Jul 2026 11:14:28 GMT",
        "receipt_filename": "gao-26-108457.pdf"
      },
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:19.128228+00:00",
        "status": 403
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash."
    },
    {
      "id": "s09",
      "publisher": "Defense Comptroller",
      "title": "FY2027 P-1 procurement programs",
      "url": "https://comptroller.war.gov/Portals/45/Documents/defbudget/FY2027/FY2027_p1.pdf",
      "document_date": "2026-04",
      "date_precision": "month",
      "locator": "PDF pp. 102–103 / printed pp. 97–98; 1506N Aircraft Procurement, Navy; row 17 MQ-25 main / Less: Advance Procurement (PY), row 18 Advance Procurement (CY); dollars in thousands. FY2026 columns are on p. 97 and FY2027 columns continue on p. 98.",
      "reviewed_at": "2026-09-12",
      "original_receipt": {
        "retrieved_at": "2026-09-12T13:56:02.675144+00:00",
        "sha256": "b8d5248257590856ee33ddb1b401ec2efcdfea219c05b5bc8ea1068d9000d0a6",
        "http_last_modified": "Fri, 03 Apr 2026 19:56:57 GMT",
        "receipt_filename": "procurement-p1-pb2027.pdf"
      },
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:17.398732+00:00",
        "status": 200,
        "sha256": "b8d5248257590856ee33ddb1b401ec2efcdfea219c05b5bc8ea1068d9000d0a6",
        "receipt": "evidence/2026-09-12/procurement-p1-pb2027.pdf",
        "unchanged_from_feasibility": true
      },
      "access_note": "Fresh anonymous HTTPS retrieval succeeded."
    },
    {
      "id": "s10",
      "publisher": "Defense Comptroller",
      "title": "FY2026 DD1414 Base for Reprogramming Actions",
      "url": "https://comptroller.war.gov/Portals/45/Documents/execution/FY_2026_DD_1414_Base_for_Reprogramming_Actions.pdf",
      "document_date": null,
      "date_precision": "not_established",
      "locator": "PDF p. 94 / printed Navy N-15; 1506N, MQ-25 and MQ-25 Advance Procurement rows; FY2026 Appropriated Base, columns b–i. Main request 407,046; reduction 19,360; resulting base 387,686 (all $000).",
      "reviewed_at": "2026-09-12",
      "original_receipt": {
        "retrieved_at": "2026-09-12T13:56:06.318968+00:00",
        "sha256": "4cef3b41d68da3812828993bbb4b110d1aca5d5b0a67b1cb9eee8961324a96a3",
        "http_last_modified": "Mon, 17 Aug 2026 18:58:32 GMT",
        "receipt_filename": "dd1414-fy2026.pdf"
      },
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:18.430540+00:00",
        "status": 200,
        "sha256": "4cef3b41d68da3812828993bbb4b110d1aca5d5b0a67b1cb9eee8961324a96a3",
        "receipt": "evidence/2026-09-12/dd1414-fy2026.pdf",
        "unchanged_from_feasibility": true
      },
      "access_note": "Fresh anonymous HTTPS retrieval succeeded."
    },
    {
      "id": "s11",
      "publisher": "Defense Comptroller",
      "title": "FY2027 R-1 research, development, test and evaluation",
      "url": "https://comptroller.war.gov/Portals/45/Documents/defbudget/FY2027/FY2027_r1.pdf",
      "document_date": "2026-04",
      "date_precision": "month",
      "locator": "PDF p. 38 / printed p. 33; 1319N, line 237, PE 0207255N MQ-25 Stingray, BA 07; FY2027 discretionary request 513,308 ($000). Read with MSAR p. 16 shared-scope notes.",
      "reviewed_at": "2026-09-12",
      "original_receipt": {
        "retrieved_at": "2026-09-12T13:56:04.709968+00:00",
        "sha256": "1aa8846edb69d4c3a54e03b383b0cabb77f93433162b8139ab8cbb55bcc7882a",
        "http_last_modified": "Fri, 03 Apr 2026 19:56:57 GMT",
        "receipt_filename": "rdte-r1-pb2027.pdf"
      },
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:18.128497+00:00",
        "status": 200,
        "sha256": "1aa8846edb69d4c3a54e03b383b0cabb77f93433162b8139ab8cbb55bcc7882a",
        "receipt": "evidence/2026-09-12/rdte-r1-pb2027.pdf",
        "unchanged_from_feasibility": true
      },
      "access_note": "Fresh anonymous HTTPS retrieval succeeded."
    },
    {
      "id": "s12",
      "publisher": "Defense Comptroller",
      "title": "FY2026 Mandatory Funding Allocation Plan",
      "url": "https://comptroller.war.gov/Portals/45/Documents/news/FY2026_Mandatory_Funding_Allocation_Plan.pdf",
      "document_date": null,
      "date_precision": "not_established",
      "locator": "PDF p. 63 / printed p. 59; Section 20007, item 14, Accelerate MQ-25 production. $100m allocation, LRIP Lot 1 intent and March 2026 planned award; summary on PDF p. 60 / printed p. 56.",
      "reviewed_at": "2026-09-12",
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:20.851827+00:00",
        "status": 200,
        "sha256": "4dcd91ae15ea37508d0d77b9fa67139c5dcf2e909b946b9339b9358cc217fd2f",
        "receipt": "evidence/2026-09-12/mandatory-allocation-fy2026.pdf"
      },
      "access_note": "Fresh anonymous HTTPS retrieval succeeded."
    },
    {
      "id": "s13",
      "publisher": "U.S. Treasury / USAspending",
      "title": "Award detail: N0001918C1012",
      "url": "https://api.usaspending.gov/api/v2/awards/CONT_AWD_N0001918C1012_9700_-NONE-_-NONE-/",
      "document_date": null,
      "date_precision": "not_established",
      "locator": "JSON pointers /piid, /generated_unique_award_id, /total_obligation, /period_of_performance/last_modified_date, /base_exercised_options and /base_and_all_options. Published aggregate is total_obligation, not either option-value field.",
      "reviewed_at": "2026-09-12",
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:21.192789+00:00",
        "status": 200,
        "sha256": "773b0ae56b403ae2fd11882c3e4cef96333313f8ea9790af39a510b9804e6077",
        "receipt": "evidence/2026-09-12/usaspending-emd.json"
      },
      "access_note": "Fresh anonymous HTTPS retrieval succeeded."
    },
    {
      "id": "s14",
      "publisher": "Department of Defense contract announcements",
      "title": "Contracts for March 29, 2024",
      "url": "https://www.war.gov/News/Contracts/Contract/Article/3725457/contracts-for-mar-29-2024/",
      "document_date": "2024-03-29",
      "date_precision": "day",
      "locator": "NAVY section, Boeing paragraph; contract N0001918C1012, modification P00067. $657,090,000 action; $288,635,000 FY2023 RDT&E obligated at award; two additional SDTA aircraft plus related scope.",
      "reviewed_at": "2026-09-12",
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:20.282488+00:00",
        "status": 403
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash.",
      "browser_review": {
        "date": "2026-09-12",
        "format": "Browser-retriever text, not original HTML bytes."
      }
    },
    {
      "id": "s15",
      "publisher": "Department of Defense contract announcements",
      "title": "Contracts for September 28, 2022",
      "url": "https://www.war.gov/News/Contracts/Contract/Article/3173663/contracts-for-sep-28-2022/",
      "document_date": "2022-09-28",
      "date_precision": "day",
      "locator": "NAVY section, Boeing $47,468,000 advance-acquisition paragraph; N0001922C0048; FY2022 aircraft procurement obligated at award. Long-lead purpose also documented in MSAR p. 8.",
      "reviewed_at": "2026-09-12",
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:20.437777+00:00",
        "status": 403
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash.",
      "browser_review": {
        "date": "2026-09-12",
        "format": "Browser-retriever text, not original HTML bytes."
      }
    },
    {
      "id": "s16",
      "publisher": "Department of War contract announcements",
      "title": "Contracts for July 17, 2026",
      "url": "https://www.war.gov/News/Contracts/Contract/Article/4549225/contracts-for-july-17-2026/",
      "document_date": "2026-07-17",
      "date_precision": "day",
      "locator": "NAVY section, first paragraph (Grunley); N40085-26-C-0017; $117,755,087 facilities contract and $65,817,578 first obligation increment from FY2024/FY2026 MILCON.",
      "reviewed_at": "2026-09-12",
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:20.623035+00:00",
        "status": 403
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash.",
      "browser_review": {
        "date": "2026-09-12",
        "format": "Browser-retriever text, not original HTML bytes."
      }
    },
    {
      "id": "s17",
      "publisher": "Department of War contract announcements",
      "title": "Contracts for August 31, 2026",
      "url": "https://www.war.gov/News/Contracts/Contract/Article/4586879/contracts-for-aug-31-2026/",
      "document_date": "2026-08-31",
      "date_precision": "day",
      "locator": "NAVY section, Boeing paragraph; N0001918C1012 / P00094; $12,680,717 action and same amount of FY2026 RDT&E to be obligated at award; component engineering / security-assessment corrections.",
      "reviewed_at": "2026-09-12",
      "original_receipt": {
        "retrieved_at": "2026-09-12T13:56:21.702503+00:00",
        "sha256": "81b670388bfb8c8445f4ee67a1be14a65b395b2fe484f379b42ac5d285ba639d",
        "http_last_modified": null,
        "receipt_filename": "contracts-20260831.html"
      },
      "direct_recheck": {
        "retrieved_at": "2026-09-12T15:18:19.630281+00:00",
        "status": 403
      },
      "access_note": "Direct HTTPS recheck was blocked. Official browser retrieval and/or the original same-day primary receipt were used. A 403 response hash is not a document hash.",
      "browser_review": {
        "date": "2026-09-12",
        "format": "Browser-retriever text, not original HTML bytes."
      }
    }
  ],
  "claims": [
    {
      "id": "c01",
      "statement": "The retrieved MSAR preserves August 2024 original IOC, July 2026 revised objective, July 2027 revised threshold and February 2029 current forecast.",
      "section": "schedule",
      "source_ids": [
        "s01"
      ],
      "locator": "PDF/printed p. 10, IOC row; pp. 10–11 deviation notes",
      "status": "reported_forecast",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c02",
      "statement": "The current IOC forecast is 54 calendar months after the original objective, 31 after the revised objective and 19 after the threshold.",
      "section": "schedule",
      "source_ids": [
        "s01"
      ],
      "locator": "p. 10 IOC row; (end_year-start_year)*12 + end_month-start_month",
      "status": "derived",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c03",
      "statement": "Navy’s August 2018 announcement describes a $805.3m contract ceiling for four development aircraft and IOC by 2024.",
      "section": "promise",
      "source_ids": [
        "s02"
      ],
      "locator": "Opening two paragraphs",
      "status": "documented",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c04",
      "statement": "The current acquisition estimate is $13,881.9m in constant 2018 dollars versus original $12,618.3m and revised $13,324.4m.",
      "section": "money",
      "source_ids": [
        "s01"
      ],
      "locator": "pp. 13,15 acquisition totals and unit cost comparison",
      "status": "estimate",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c05",
      "statement": "The planned total stays 76 aircraft while development/procurement changes 4/72 to 9/67; ground stations excluded.",
      "section": "money",
      "source_ids": [
        "s01"
      ],
      "locator": "p. 13 End-Item Quantity and Quantity Unit Description",
      "status": "planned_quantity",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c06",
      "statement": "Current then-year acquisition and O&S estimates are separately $19,440.8m and $37,019.3m. O&S assumes 74 aircraft to sustain, 20-year unit life and operations FY2029–FY2059.",
      "section": "money",
      "source_ids": [
        "s01"
      ],
      "locator": "p. 13 Total Acquisition; p. 18 Total O&S; p. 19 O&S Cost Estimate Assumptions",
      "status": "estimate",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c07",
      "statement": "Source-reported appropriations and expenditures actual to date are $4,434.9m and $2,328.1m, without a distinct transaction cutoff.",
      "section": "money",
      "source_ids": [
        "s01"
      ],
      "locator": "p. 25 Acquisition Funding",
      "status": "reported_aggregate",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c08",
      "statement": "FY2026 main procurement appropriated base is $387.686m after a $19.360m reduction from $407.046m; advance procurement is $52.191m.",
      "section": "money",
      "source_ids": [
        "s10",
        "s09"
      ],
      "locator": "DD1414 PDF p. 94 / N-15; P-1 PDF p. 102 / p. 97",
      "status": "appropriated_base",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c09",
      "statement": "P-1 shows a separate $100m FY2026 PL119-21 spending-plan column; allocation narrative retains a planned March 2026 Lot 1 award, not an actual.",
      "section": "money",
      "source_ids": [
        "s09",
        "s12"
      ],
      "locator": "P-1 row 17; allocation plan PDF p. 63 / p. 59 item 14",
      "status": "spending_plan",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c10",
      "statement": "FY2027 main request is $823.368m gross minus $52.191m prior-year advance procurement, or $771.177m net; $80.965m new advance procurement is separate.",
      "section": "money",
      "source_ids": [
        "s09"
      ],
      "locator": "PDF p. 103 / p. 98 rows 17–18",
      "status": "request",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c11",
      "statement": "FY2027 PE 0207255N request is $513.308m; MSAR records realignment from 0605414N and Shared notes with distinct FY2018 and Stingray to the Fight scopes.",
      "section": "money",
      "source_ids": [
        "s01",
        "s11"
      ],
      "locator": "MSAR p. 16; R-1 PDF p. 38 / p. 33 line 237",
      "status": "shared_scope",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c12",
      "statement": "The program-to-EMD-award link is explicit, including Boeing, CAGE 76301, N00019-18-C-1012 and selected Air System CLINs.",
      "section": "contracts",
      "source_ids": [
        "s01"
      ],
      "locator": "p. 22 Contracts and Efforts / effort description",
      "status": "identifier",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c13",
      "statement": "The EMD award API reports $1,843,827,977.96 cumulative obligations and June 1 last modification on fresh September 12 retrieval.",
      "section": "contracts",
      "source_ids": [
        "s13"
      ],
      "locator": "/total_obligation; /period_of_performance/last_modified_date",
      "status": "obligation_aggregate",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c14",
      "statement": "P00067 adds two SDTA aircraft and other work; $657.09m action value and $288.635m obligation at award differ.",
      "section": "contracts",
      "source_ids": [
        "s14"
      ],
      "locator": "NAVY Boeing P00067 paragraph",
      "status": "announced_contract_action",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c15",
      "statement": "Norfolk facilities award is $117,755,087 with first obligation increment $65,817,578.",
      "section": "contracts",
      "source_ids": [
        "s16"
      ],
      "locator": "NAVY Grunley N40085-26-C-0017 paragraph",
      "status": "announced_contract_action",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c16",
      "statement": "August 31 P00094 is $12,680,717 in engineering/integration scope with the same amount announced obligated at award.",
      "section": "contracts",
      "source_ids": [
        "s17"
      ],
      "locator": "NAVY Boeing N0001918C1012 / P00094 paragraph",
      "status": "announced_contract_action",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c17",
      "statement": "T1 refueled three receiver aircraft types in 2021; F-35C event September 13.",
      "section": "outcomes",
      "source_ids": [
        "s04"
      ],
      "locator": "Opening and third-refueling-flight paragraphs",
      "status": "demonstrated_prototype",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c18",
      "statement": "T1 completed carrier deck handling demonstrations in December 2021, not carrier flight.",
      "section": "outcomes",
      "source_ids": [
        "s05"
      ],
      "locator": "Body paragraphs about T1 underway tests",
      "status": "demonstrated_prototype",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c19",
      "statement": "DOT&E reports receipt of a first air test vehicle May 2025; MSAR dates EDM3 assembly completion July 2025; no equivalent acceptance criteria are established.",
      "section": "outcomes",
      "source_ids": [
        "s03",
        "s01"
      ],
      "locator": "DOT&E pp. 177–178; MSAR p. 7; p. 25 blank end-item delivery cells",
      "status": "bounded_gap",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c20",
      "statement": "EDM3 completed fleet-representative first flight April 25, 2026, about two hours under UMCS control.",
      "section": "outcomes",
      "source_ids": [
        "s01",
        "s06"
      ],
      "locator": "MSAR p. 8; NAVAIR first two body paragraphs",
      "status": "actual_test",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c21",
      "statement": "Milestone C decision dated May 18 authorizes two three-aircraft LRIP lots and advance acquisition for Lot3; news date May19.",
      "section": "outcomes",
      "source_ids": [
        "s01",
        "s07"
      ],
      "locator": "MSAR pp. 8,10,24; Navy May19 opening paragraph",
      "status": "approved",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c22",
      "statement": "Carrier suitability and full refueling requirement remain TBD in MSAR demonstrated-performance cells; 16,000 lb objective differs from 14,000 lb threshold/current estimate at 500 nm.",
      "section": "outcomes",
      "source_ids": [
        "s01"
      ],
      "locator": "p. 12 KPP1 and KPP2",
      "status": "not_demonstrated_in_source",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c23",
      "statement": "DOT&E’s FY2025 report finds insufficient evidence to evaluate effectiveness/suitability/survivability and recommends an adequate OA before IOC.",
      "section": "outcomes",
      "source_ids": [
        "s03"
      ],
      "locator": "pp. 178–179 Performance / Recommendation",
      "status": "retrospective_assessment",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c24",
      "statement": "MSAR cover date precedes the latest modification and later actual milestones; publication timing of all facts is not established.",
      "section": "limits",
      "source_ids": [
        "s01"
      ],
      "locator": "pp. 1,8,10,22,24 and original HTTP metadata",
      "status": "version_date_limit",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c25",
      "statement": "MSAR LRIP percentage/denominator and >10% rationale are internally inconsistent; this edition uses authorized lots, not the disputed ratio.",
      "section": "limits",
      "source_ids": [
        "s01"
      ],
      "locator": "pp. 13 and 24",
      "status": "source_conflict",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c26",
      "statement": "Theodore Roosevelt UAWC is reported deployable in March2026; Ronald Reagan end-August target remains unverified as an actual event here.",
      "section": "outcomes",
      "source_ids": [
        "s01"
      ],
      "locator": "p. 7 second substantive paragraph",
      "status": "subsystem_status",
      "reviewed_at": "2026-09-12"
    },
    {
      "id": "c27",
      "statement": "First operational delivery is forecast FY2028; actual end-item totals are unreported rather than zero.",
      "section": "outcomes",
      "source_ids": [
        "s01"
      ],
      "locator": "p. 25 End Items Delivered / First Operational Delivery",
      "status": "forecast_and_missing_data",
      "reviewed_at": "2026-09-12"
    }
  ],
  "schedule": [
    {
      "id": "first-flight",
      "event": "Fleet-representative first flight",
      "original": "2021-09",
      "revised_objective": "2025-05",
      "revised_threshold": "2025-11",
      "forecast": null,
      "actual": "2026-04-25",
      "source_id": "s01",
      "locator": "PDF/printed p. 10, Schedule Events",
      "original_baseline_date": "2018-08-24",
      "revised_baseline_date": "2024-09-12",
      "estimate_label": "2026-04-21; retrieved version includes later events"
    },
    {
      "id": "lrip",
      "event": "Low-rate production decision",
      "original": "2023-02",
      "revised_objective": "2025-06",
      "revised_threshold": "2025-12",
      "forecast": null,
      "actual": "2026-05-18",
      "source_id": "s01",
      "locator": "PDF/printed p. 10, Schedule Events",
      "original_baseline_date": "2018-08-24",
      "revised_baseline_date": "2024-09-12",
      "estimate_label": "2026-04-21; retrieved version includes later events"
    },
    {
      "id": "carrier-flight",
      "event": "First carrier flight",
      "original": "2022-12",
      "revised_objective": "2026-03",
      "revised_threshold": "2027-03",
      "forecast": "2027-02",
      "actual": null,
      "source_id": "s01",
      "locator": "PDF/printed p. 10, Schedule Events",
      "original_baseline_date": "2018-08-24",
      "revised_baseline_date": "2024-09-12",
      "estimate_label": "2026-04-21; retrieved version includes later events"
    },
    {
      "id": "ioc",
      "event": "Initial operational capability",
      "original": "2024-08",
      "revised_objective": "2026-07",
      "revised_threshold": "2027-07",
      "forecast": "2029-02",
      "actual": null,
      "source_id": "s01",
      "locator": "PDF/printed p. 10, Schedule Events",
      "original_baseline_date": "2018-08-24",
      "revised_baseline_date": "2024-09-12",
      "estimate_label": "2026-04-21; retrieved version includes later events"
    },
    {
      "id": "iote",
      "event": "Initial operational test & evaluation",
      "original": "2024-01",
      "revised_objective": "2026-11",
      "revised_threshold": "2028-05",
      "forecast": "2029-02",
      "actual": null,
      "source_id": "s01",
      "locator": "PDF/printed p. 10, Schedule Events",
      "original_baseline_date": "2018-08-24",
      "revised_baseline_date": "2024-09-12",
      "estimate_label": "2026-04-21; retrieved version includes later events"
    },
    {
      "id": "frp",
      "event": "Full-rate production decision",
      "original": "2026-04",
      "revised_objective": "2028-01",
      "revised_threshold": "2029-07",
      "forecast": "2030-04",
      "actual": null,
      "source_id": "s01",
      "locator": "PDF/printed p. 10, Schedule Events",
      "original_baseline_date": "2018-08-24",
      "revised_baseline_date": "2024-09-12",
      "estimate_label": "2026-04-21; retrieved version includes later events"
    }
  ],
  "timeline": [
    {
      "id": "event-01",
      "date": "2018-08-30",
      "category": "Contract",
      "status": "actual",
      "title": "Development award",
      "text": "Boeing receives the initial development award: $805.3m ceiling, four aircraft, stated IOC by 2024.",
      "source_id": "s02"
    },
    {
      "id": "event-02",
      "date": "2019-09",
      "category": "Test",
      "status": "actual",
      "title": "T1 flies",
      "text": "First flight of the Boeing-owned demonstrator; not the later fleet-representative milestone.",
      "source_id": "s01"
    },
    {
      "id": "event-03",
      "date": "2021-09-13",
      "category": "Test",
      "status": "actual",
      "title": "Three receiver types demonstrated",
      "text": "T1 refuels an F-35C, after F/A-18 and E-2D demonstrations earlier in 2021.",
      "source_id": "s04"
    },
    {
      "id": "event-04",
      "date": "2021-12",
      "category": "Test",
      "status": "actual",
      "title": "Carrier deck demonstration",
      "text": "T1 day/night deck-handling work aboard USS George H.W. Bush; not a carrier launch or recovery.",
      "source_id": "s05"
    },
    {
      "id": "event-05",
      "date": "2022-09-28",
      "category": "Contract",
      "status": "actual",
      "title": "Long-lead procurement",
      "text": "$47.468m advance-acquisition award for LRIP Lot 1. Not delivery of the lot.",
      "source_id": "s15"
    },
    {
      "id": "event-06",
      "date": "2023-10",
      "category": "Funding",
      "status": "reported_actual",
      "title": "Development extension changes funding",
      "text": "MSAR records approval of an above-threshold reprogramming from procurement to RDT&E after the LRIP delay; this edition does not reconcile the transfer amount.",
      "source_id": "s01"
    },
    {
      "id": "event-07",
      "date": "2024-03-29",
      "category": "Contract",
      "status": "actual",
      "title": "Two more demonstration aircraft",
      "text": "P00067 adds SDTA aircraft and related tooling/obsolescence work. $657.09m action; $288.635m obligated at award.",
      "source_id": "s14"
    },
    {
      "id": "event-08",
      "date": "2024-09-12",
      "category": "Decision",
      "status": "actual",
      "title": "Baseline revised",
      "text": "EMD extension reflected in a revised APB; IOC objective July 2026, threshold July 2027.",
      "source_id": "s01"
    },
    {
      "id": "event-09",
      "date": "2025-05",
      "category": "Delivery",
      "status": "reported_actual",
      "title": "First air test vehicle received",
      "text": "DOT&E reports Navy receipt; not a formal-acceptance tally or an operational delivery.",
      "source_id": "s03"
    },
    {
      "id": "event-10",
      "date": "2026-03",
      "category": "Delivery",
      "status": "reported_actual",
      "title": "Carrier control infrastructure",
      "text": "MSAR reports a deployable MQ-25-capable UAWC aboard USS Theodore Roosevelt. The air system has not thereby reached IOC.",
      "source_id": "s01"
    },
    {
      "id": "event-11",
      "date": "2026-04-25",
      "category": "Test",
      "status": "actual",
      "title": "EDM 3 takes flight",
      "text": "First fleet-representative flight, approximately two hours, using the UMCS ground-control system.",
      "source_id": "s06"
    },
    {
      "id": "event-12",
      "date": "2026-05-18",
      "category": "Decision",
      "status": "actual",
      "title": "Production approved",
      "text": "Milestone C / KP-6 approves entry into production and deployment; Navy announces it May 19. Not IOC.",
      "source_id": "s01"
    },
    {
      "id": "event-13",
      "date": "2026-07-17",
      "category": "Contract",
      "status": "actual",
      "title": "Norfolk facilities awarded",
      "text": "MQ-25 laydown construction contract: $117.755087m value, $65.817578m first obligation increment.",
      "source_id": "s16"
    },
    {
      "id": "event-14",
      "date": "2026-08-31",
      "category": "Contract",
      "status": "actual",
      "title": "EMD engineering scope added",
      "text": "P00094: $12.680717m for component integration and security-assessment corrections, obligated at award per announcement.",
      "source_id": "s17"
    },
    {
      "id": "event-15",
      "date": "2027-02",
      "category": "Test",
      "status": "forecast",
      "title": "First carrier flight",
      "text": "Current MSAR forecast; no actual carrier flight established by this edition.",
      "source_id": "s01"
    },
    {
      "id": "event-16",
      "date": "FY2028",
      "category": "Delivery",
      "status": "forecast",
      "title": "First operational delivery",
      "text": "Fielding-plan forecast, not test-vehicle receipt and not IOC.",
      "source_id": "s01"
    },
    {
      "id": "event-17",
      "date": "2029-02",
      "category": "Decision",
      "status": "forecast",
      "title": "Initial operational capability",
      "text": "Current forecast, 54 months after the original August 2024 objective.",
      "source_id": "s01"
    }
  ],
  "acquisition_estimates": [
    {
      "category": "RDT&E",
      "original": 3489.3,
      "revised": 3691.5,
      "current": 4013.0,
      "current_then_year": 5011.4,
      "units": "USD millions",
      "comparison_price_basis": "constant 2018 dollars",
      "then_year_price_basis": "then-year dollars",
      "stage": "estimate",
      "source_id": "s01",
      "locator": "PDF/printed p. 13; objective columns and PB2027 current estimate"
    },
    {
      "category": "Procurement",
      "original": 8766.1,
      "revised": 9048.2,
      "current": 9168.3,
      "current_then_year": 13449.2,
      "units": "USD millions",
      "comparison_price_basis": "constant 2018 dollars",
      "then_year_price_basis": "then-year dollars",
      "stage": "estimate",
      "source_id": "s01",
      "locator": "PDF/printed p. 13; objective columns and PB2027 current estimate"
    },
    {
      "category": "Military construction",
      "original": 362.9,
      "revised": 584.7,
      "current": 700.6,
      "current_then_year": 980.2,
      "units": "USD millions",
      "comparison_price_basis": "constant 2018 dollars",
      "then_year_price_basis": "then-year dollars",
      "stage": "estimate",
      "source_id": "s01",
      "locator": "PDF/printed p. 13; objective columns and PB2027 current estimate"
    },
    {
      "category": "Total acquisition",
      "original": 12618.3,
      "revised": 13324.4,
      "current": 13881.9,
      "current_then_year": 19440.8,
      "units": "USD millions",
      "comparison_price_basis": "constant 2018 dollars",
      "then_year_price_basis": "then-year dollars",
      "stage": "estimate",
      "source_id": "s01",
      "locator": "PDF/printed p. 13; objective columns and PB2027 current estimate"
    }
  ],
  "funding": [
    {
      "id": "fy26-main-request",
      "fiscal_year": 2026,
      "scope": "Aircraft Procurement, Navy / main MQ-25 row",
      "stage": "request",
      "amount": 407.046,
      "units": "USD millions",
      "price_basis": "nominal fiscal-year dollars",
      "note": "FY2026 original request shown in DD1414",
      "source_id": "s10"
    },
    {
      "id": "fy26-main-enacted",
      "fiscal_year": 2026,
      "scope": "Aircraft Procurement, Navy / main MQ-25 row",
      "stage": "appropriated_base",
      "amount": 387.686,
      "units": "USD millions",
      "price_basis": "nominal fiscal-year dollars",
      "note": "FY2026 discretionary enacted / appropriated base",
      "source_id": "s10"
    },
    {
      "id": "fy26-main-plan",
      "fiscal_year": 2026,
      "scope": "Aircraft Procurement, Navy / main MQ-25 row",
      "stage": "spending_plan",
      "amount": 100.0,
      "units": "USD millions",
      "price_basis": "nominal fiscal-year dollars",
      "note": "FY2026 PL119-21 spending-plan column; not an obligation",
      "source_id": "s09"
    },
    {
      "id": "fy26-advance",
      "fiscal_year": 2026,
      "scope": "Aircraft Procurement, Navy / advance procurement",
      "stage": "appropriated_base",
      "amount": 52.191,
      "units": "USD millions",
      "price_basis": "nominal fiscal-year dollars",
      "note": "Advance procurement for FY2027, separate row",
      "source_id": "s10"
    },
    {
      "id": "fy27-main-net",
      "fiscal_year": 2027,
      "scope": "Aircraft Procurement, Navy / main MQ-25 row",
      "stage": "request",
      "amount": 771.177,
      "units": "USD millions",
      "price_basis": "nominal fiscal-year dollars",
      "note": "Net after prior-year advance procurement; three-aircraft budget quantity",
      "source_id": "s09"
    },
    {
      "id": "fy27-advance",
      "fiscal_year": 2027,
      "scope": "Aircraft Procurement, Navy / advance procurement",
      "stage": "request",
      "amount": 80.965,
      "units": "USD millions",
      "price_basis": "nominal fiscal-year dollars",
      "note": "New advance procurement for FY2028, separate row",
      "source_id": "s09"
    },
    {
      "id": "fy27-rdte-shared",
      "fiscal_year": 2027,
      "scope": "RDT&E, Navy / PE 0207255N (shared)",
      "stage": "request",
      "amount": 513.308,
      "units": "USD millions",
      "price_basis": "nominal fiscal-year dollars",
      "note": "Entire PE request; no supported MQ-25 Air System-only split",
      "source_id": "s11"
    }
  ],
  "contracts": [
    {
      "id": "emd-original",
      "date": "2018-08-30",
      "title": "Boeing · original development",
      "piid": "N00019-18-C-1012",
      "modification": null,
      "value": 805300000,
      "obligation_at_award": null,
      "value_stage": "ceiling",
      "note": "Initial four-aircraft development scope. Not a fleet-wide cap.",
      "source_id": "s02",
      "units": "USD",
      "price_basis": "nominal action dollars",
      "obligation_evidence": "not reported in cited announcement"
    },
    {
      "id": "lrip-aac",
      "date": "2022-09-28",
      "title": "Boeing · advance acquisition",
      "piid": "N0001922C0048",
      "modification": null,
      "value": 47468000,
      "obligation_at_award": 47468000,
      "value_stage": "contract_award_value",
      "note": "LRIP Lot 1 long-lead procurement; not an aircraft-delivery event.",
      "source_id": "s15",
      "units": "USD",
      "price_basis": "nominal action dollars",
      "obligation_evidence": "official announcement"
    },
    {
      "id": "emd-p00067",
      "date": "2024-03-29",
      "title": "Boeing · development expansion",
      "piid": "N0001918C1012",
      "modification": "P00067",
      "value": 657090000,
      "obligation_at_award": 288635000,
      "value_stage": "modification_value",
      "note": "Two additional SDTA aircraft, tooling, communications and obsolescence work.",
      "source_id": "s14",
      "units": "USD",
      "price_basis": "nominal action dollars",
      "obligation_evidence": "official announcement"
    },
    {
      "id": "norfolk",
      "date": "2026-07-17",
      "title": "Grunley · Norfolk facilities",
      "piid": "N40085-26-C-0017",
      "modification": null,
      "value": 117755087,
      "obligation_at_award": 65817578,
      "value_stage": "contract_award_value",
      "note": "Incrementally funded construction; not aircraft procurement.",
      "source_id": "s16",
      "units": "USD",
      "price_basis": "nominal action dollars",
      "obligation_evidence": "official announcement"
    },
    {
      "id": "emd-p00094",
      "date": "2026-08-31",
      "title": "Boeing · engineering / integration",
      "piid": "N0001918C1012",
      "modification": "P00094",
      "value": 12680717,
      "obligation_at_award": 12680717,
      "value_stage": "modification_value",
      "note": "Component updates and mission-computer security-assessment corrections.",
      "source_id": "s17",
      "units": "USD",
      "price_basis": "nominal action dollars",
      "obligation_evidence": "official announcement"
    }
  ],
  "outcomes": [
    {
      "id": "t1-refueling",
      "label": "Aerial refueling",
      "date": "2021",
      "status": "demonstrated_prototype",
      "result": "T1 refueled F/A-18, E-2D and F-35C aircraft.",
      "limit": "Boeing-owned prototype; not proof of the fleet system’s complete refueling requirement.",
      "source_id": "s04"
    },
    {
      "id": "deck-demo",
      "label": "Carrier deck handling",
      "date": "2021-12",
      "status": "demonstrated_prototype",
      "result": "T1 completed day/night deck-handling tests aboard USS George H.W. Bush.",
      "limit": "Deck integration is not carrier launch/recovery or operational tanker service.",
      "source_id": "s05"
    },
    {
      "id": "test-receipt",
      "label": "Development test-vehicle receipt",
      "date": "2025-05",
      "status": "reported_receipt",
      "result": "DOT&E reports Navy receipt of the first air test vehicle.",
      "limit": "No reconciled formal-acceptance or September 12 delivered total; assembly milestones use different descriptions.",
      "source_id": "s03"
    },
    {
      "id": "edm-flight",
      "label": "Fleet-representative flight",
      "date": "2026-04-25",
      "status": "demonstrated_test",
      "result": "EDM 3 flew for approximately two hours with UMCS control; basic handling and systems tested.",
      "limit": "Not carrier flight, completed operational testing or IOC.",
      "source_id": "s06"
    },
    {
      "id": "lrip-approval",
      "label": "Production authority",
      "date": "2026-05-18",
      "status": "approved",
      "result": "Milestone C approves LRIP Lots 1 and 2 (three aircraft each) and Lot 3 advance acquisition.",
      "limit": "Authority to award contracts, not proof of those awards or six delivered aircraft.",
      "source_id": "s01"
    },
    {
      "id": "kpps",
      "label": "Full refueling / carrier-suitability requirements",
      "date": "2026-04-21 (report label)",
      "status": "not_yet_demonstrated_in_source",
      "result": "MSAR demonstrated-performance cells remain TBD.",
      "limit": "At least 14,000 lb at 500 nm is the current estimate/threshold; 16,000 lb is the objective. Nimitz/Ford suitability is not marked demonstrated.",
      "source_id": "s01"
    },
    {
      "id": "ioc",
      "label": "Initial operational capability",
      "date": "2029-02",
      "status": "forecast",
      "result": "February 2029 in the reviewed MSAR.",
      "limit": "Not an actual operational declaration. First operational delivery is separately forecast for FY2028.",
      "source_id": "s01"
    }
  ],
  "identifiers": [
    {
      "id": "mq25-identity",
      "question_id": "identity",
      "statement": "The MSAR identifies the full program name as MQ-25 Stingray, short name MQ-25, PNO 462, with Department of the Navy as lead component.",
      "source_id": "mq25-msar-pb2027",
      "locator": "PDF page 5; printed page 5; Program Description, Full Name / Short Name / PNO / Lead Component",
      "as_of": "2026-09-12",
      "scope": "Identity in the retrieved FY2027 President's Budget MSAR; PNO 462 is the MSAR program identifier, not a contract or budget-line identifier.",
      "kind": "identity",
      "status": "documented"
    },
    {
      "id": "mq25-mission-scope",
      "question_id": "identity",
      "statement": "The stated mission is to develop and deliver integrated unmanned air systems for nuclear-powered aircraft carriers as part of the Carrier Air Wing, with aerial refueling as the primary mission and intelligence, surveillance and reconnaissance as the secondary mission.",
      "source_id": "mq25-msar-pb2027",
      "locator": "PDF page 5; printed page 5; Program Description, Mission",
      "as_of": "2026-09-12",
      "scope": "Declared program mission, not a finding that the capability has been delivered or demonstrated.",
      "kind": "identity",
      "status": "documented"
    },
    {
      "id": "mq25-rdte-crosswalk",
      "question_id": "budget_links",
      "statement": "The acquisition funding table maps RDT&E account 1319N, BA 05, line/PE 0605414N (Unmanned Carrier Aviation), project 3278 (MQ-25 Air System), and states funding was realigned in FY2027 to PE 0207255N; the destination row is account 1319N, BA 07, line/PE 0207255N (MQ-25 Stingray), project 3278.",
      "source_id": "mq25-msar-pb2027",
      "locator": "PDF page 16; printed page 16; Funding Sources, Acquisition Budget Lines, first two RDT&E rows and intervening note",
      "as_of": "2026-09-12",
      "scope": "FY2027 President's Budget report crosswalk and stated FY2027 realignment. The table alone does not establish the full first/last funded-year history or executed transfers.",
      "kind": "identifier",
      "status": "documented"
    },
    {
      "id": "mq25-shared-scope",
      "question_id": "budget_links",
      "statement": "Both RDT&E rows are marked Shared. The 0605414N note says project 3278 is shared with the Unmanned Carrier Aviation Mission Control System only through FY2018; the 0207255N row notes a shared PU with Stingray to the Fight. The table defines Shared as including funding for activities outside the program within the budget year or remainder of the FYDP.",
      "source_id": "mq25-msar-pb2027",
      "locator": "PDF page 16; printed page 16; Funding Sources, Shared definition and RDT&E row notes",
      "as_of": "2026-09-12",
      "scope": "Retain the explicit FY2018 historical boundary and FY2027 report/FYDP context. Do not equate all funding under either PE with MQ-25 Air System funding; PU is retained as the document's unexplained label.",
      "kind": "identifier",
      "status": "documented"
    },
    {
      "id": "mq25-procurement-crosswalk",
      "question_id": "budget_links",
      "statement": "The acquisition procurement table maps MQ-25 line item 0449 to account 1506N, BA 04, PE 0207255N; spares and repair parts line 0605 to 1506N, BA 06, PE 0207255N, with the note J0449/J0930/J9401 Spares for MQ-25 UAV; and an OTHER placeholder row to a note specifying BA 04, line item 0449C, PE 0207255N.",
      "source_id": "mq25-msar-pb2027",
      "locator": "PDF page 16; printed page 16; Funding Sources, Acquisition Budget Lines, Procurement rows and notes",
      "as_of": "2026-09-12",
      "scope": "FY2027 President's Budget report mappings, not a complete fiscal history. Blank Shared cells do not independently establish exclusive MQ-25 ownership of all dollars under a line. Preserve the OTHER/XX/XXX placeholders separately from the more specific 0449C note. This packet does not infer the function of 0449C.",
      "kind": "identifier",
      "status": "documented"
    },
    {
      "id": "mq25-emd-award-link",
      "question_id": "award_link",
      "statement": "The MSAR explicitly lists contract N00019-18-C-1012, effort 1, as MQ-25 Engineering and Manufacturing Development (EMD), with The Boeing Company as contractor and Development as the supported phase; the detailed block gives CAGE 76301 and Naval Air Systems Command as contracting office.",
      "source_id": "mq25-msar-pb2027",
      "locator": "PDF page 22; printed page 22; Performing Activities and Contracts, Contracts and Efforts table and Contract and Effort Identification block",
      "as_of": "2026-09-12",
      "scope": "Documentary program-to-contract bridge, not a name-only search match. N0001918C1012 is a deterministic hyphen-removal lookup form of the printed contract number, not a separately established award-database match. Effort scope is Air System CLINs 0001, 0005, 0008 and 0009; no claim of complete program-contract coverage or whole-program accounting.",
      "kind": "identifier",
      "status": "documented"
    }
  ],
  "financial_comparisons": {
    "fy2026_main_request_usd": 407046000,
    "fy2026_reduction_usd": 19360000,
    "fy2026_main_appropriated_base_usd": 387686000,
    "fy2026_pl11921_spending_plan_usd": 100000000,
    "fy2026_main_total_usd": 487686000,
    "fy2027_gross_usd": 823368000,
    "fy2027_prior_year_advance_deduction_usd": 52191000,
    "fy2027_net_request_usd": 771177000,
    "fy2027_new_advance_request_usd": 80965000
  },
  "emd_award_snapshot": {
    "piid": "N0001918C1012",
    "total_obligation_usd": 1843827977.96,
    "last_modified_date": "2026-06-01",
    "retrieved_at": "2026-09-12T15:18:21.192789+00:00",
    "source_id": "s13",
    "scope": "Single award; no manual addition of later contract announcements."
  },
  "operating_and_support_estimate": {
    "then_year_usd_millions": 37019.3,
    "constant_2018_usd_millions": 19685.4,
    "stage": "estimate",
    "quantity_to_sustain": 74,
    "unit_expected_service_life_years": 20,
    "operational_fiscal_years": {
      "start": 2029,
      "end": 2059
    },
    "source_id": "s01",
    "locator": "PDF/printed pp. 18–19, Total O&S and Cost Estimate Assumptions",
    "limit": "Separate cost category and denominator; not spending to date or part of the acquisition estimate."
  },
  "delivery_snapshot": {
    "cutoff": "2026-09-12T15:30:00Z",
    "accepted_aircraft_total": null,
    "delivered_aircraft_total": null,
    "status": "not_reconciled_in_reviewed_public_evidence",
    "source_ids": [
      "s01",
      "s03"
    ],
    "locators": [
      "MSAR PDF/printed p. 25; end-item actual cells blank/dashes",
      "DOT&E PDF pp. 188–189 / printed pp. 177–178; first air test vehicle received May2025"
    ],
    "note": "Missing fleet totals are not zero. Contract-effort delivered quantity is not an aircraft fleet count."
  },
  "material_limits": [
    "No reconciled September12 delivery/acceptance total",
    "No independently verified post-Milestone-C LRIP production award or superseding APB",
    "Shared RDT&E row cannot be wholly attributed to Air System",
    "Cover/version/event dates differ",
    "Retrospective independent test assessment",
    "Selected financial and contract records, not complete program accounting",
    "Internal LRIP denominator/percentage inconsistency is not repaired",
    "Some direct-source rechecks blocked; earlier receipts and browser views retained"
  ]
}